Jones & Wagener was appointed by BECSA (Billiton Energy Coal South Africa) as one of three EPCMs on the Douglas Middleburg Optimisation Project (DMO). J&W was responsible for the geotechnical investigations of all the infrastructure and the design and construction management of 5 contract packages that ran simultaneously.
The project scope included:
The project cost was well above 1 billion Rand, and the project has been completed successfully in 33 months. Challenges included accommodating continuing mining activities, a very tight schedule that also had to accommodate significant scope changes.